Jump To Navigation
Serving the Construction Industry

September 2008 Newsletter

Babcock Scott Babcock Newsletter
September, 2008

Hard Hat Case Note


EDSA/Cloward, LLC v. Klibanoff

In July of 2008, the Utah Court of Appeals decided EDSA/Cloward, LLC v. Klibanoff, 2008 UT App 284, a case involving mechanic's lien priority under the mechanic's lien statute. In the fall of 2000, EDSA, a consulting engineering firm specializing in water projects, entered into an oral contract with a developer to provide various services in connection with a luxury condominium project in Midway, Utah. To fund the Project, the developer obtained financing, which was secured by a trust deed recorded on June 15, 2001, and later assigned to Daniel Klibanoff. EDSA performed not only design services but also placed survey stakes and pin flags, installed ground water monitoring stations, replaced a decrepit underground pipe used to direct water from an irrigation ditch, and other physical work it performed on the property. On November 8, 2002, EDSA recorded a mechanic's lien to recover more than $555,000 in unpaid services.

In response to EDSA's Complaint, Klibanoff claimed that his trust deed had priority over the mechanic's lien EDSA recorded. After trial, the trial court found that while EDSA had indeed performed work on the property, the work "had to be performed before EDSA[ ] could complete the design of the Project." The trial court also found that these activities "were prerequisites to obtaining preliminary and final approvals for the Project from Midway City and the required permit from the U.S. Army Corps of Engineers," all of which "were required in advance of commencing construction." Finally, the trial court found that EDSA's irrigation improvements were nothing more than "ordinary maintenance of an existing irrigation system."

Based on these findings, which EDSA did not dispute , the trial court held that there was no visible commencement of work on the project prior to June 15, 2001, the date Klibanhoff's trust deed was recorded. Therefore, the trial court ruled that Klibanoff's interest in the property was superior to EDSA's lien, and awarded Klibanoff his attorney fees and costs pursuant to Utah Code section 38-1-18.

EDSA appealed the trial court's ruling, arguing that the trial court's factual findings were insufficient to support its holding that no work was visibly commenced and no materials were furnished on the ground at the project before June 15, 2001. EDSA also argued that the trial court erred in awarding Klibanoff his attorney fees and costs because both it and Klibanoff were successful parties, that the affidavit of attorney fees from Klibanoff's counsel was deficient, and that the amount of fees awarded was unreasonable.

The Utah Court of Appeals first examined EDSA's priority argument in relation to Utah Code section 38-1-5, which provides that mechanic's liens relate back to:

the time of the commencement to do work or furnish materials on the ground for the structure or improvement, and shall have priority over any lien, mortgage or other encumbrance which may have attached subsequently to the time when the building, improvement or structure was commenced, work begun, or first material furnished on the ground.The Court of Appeals held that none of the physical work EDSA performed on the property was sufficient to satisfy this statute because the nature of the work performed and the minimal visible evidence of that work did not suggest an impending or ongoing construction project on the property. Without this evidence to "the world" of construction commencement, EDSA's lien took effect after Klibanhoff's trust deed was recorded. Consequently, Klibanhoff's trust deed had priority over EDSA's mechanic's lien.

-------------------------------------------------------------------------------------

The Construction Attorney's Toolbox-Building Solutions Through Mediation

By Kent B. Scott

Introduction

Today's current economic climate challenges owners and contractors to complete projects in less time for less money. These pressures have created more demanding time schedules and monetary budgets that, in turn, have created an increased number of disputes. Another developing trend is the increased costs in time, money, efficiencies and lost opportunities taken up by these disputes. The legal fees and costs incurred in resolving disputes become a major component of the dispute. The dollars that should go into project profits are now going into the resolution of project disputes.

The creation of a construction project is both a science and an art requiring the parties to define, design, build, pay and negotiate with each other to produce the desired result. The expectations of the parties involved with a project do not always result in a meeting of the minds. Differences in what was wanted, the completion date and the price paid can give rise to conflict in many forms. Most conflicts are readily resolved, but some continue to fester and grow. Some disputes find their way into legal counsel's office where the client seeks assistance in solving the problem.

This article will discuss the basic concepts of mediation as one of the tools that is used by clients and their attorneys to resolve construction project claims.

Mediation Defined

Mediation is a procedure where two or more parties attempt to resolve their dispute with a neutral party-the mediator. The mediator remains neutral throughout the meeting. The process is confidential. No resolution can be reached without the consent of the parties. If an agreement is reached, the agreement will be binding and can be enforced by the courts.

Anatomy of a Successful Mediation

The success of a mediation is controlled mainly by the parties. Some of the critical components of a successful mediation include:

The background and capabilities of the mediator.

The attendance, commitment of informed people with authority to settle.

The needs and interests of the parties.

Whether a trial or arbitration has been scheduled.

Commitment of the parties and their attorneys to participate.

The following is a brief outline of the events involved in a mediation:

The parties sign a confidentiality statement.

The attorneys prepare a short and confidential written statement for the mediator.•· The parties summarize their positions in a joint session.

The parties go into separate confidential meetings .

The mediator shuttles between the parties in an effort to find common ground.

If a settlement is reached, a written agreement is created .

If a settlement is not achieved another session may be scheduled or the mediator may offer some suggestions to consider that may assist the parties in future negotiations.

When and Where to Mediate

There is no set formula to ensure that a mediation will succeed. Mediation can be effective at any stage of the dispute: pre-litigation, during litigation, on appeal, etc. Most mediations occur after a claim has been filed and some exchange of information has taken place. The decision as to whether or when to mediate will vary with each case.

Who Should Come to the Mediation

The following is a brief summary of those who would be expected to attend the mediation:

•· Legal counsel. Yes, if the party is represented.

•· Client. The person with authority to settle and others with knowledge of the facts.

•· Experts. Use experts carefully. Experts often complicate the settlement process. However, they may be helpful to describe and simplify technical information.

•· Documents. Less is better. Summaries, graphs and charts are useful.

•· Support Personnel. Associates, secretaries or assistants are discouraged. If there is a need, make advanced arrangements so all parties approve and understand their respective roles.

Making the First Move

There is no advantage for one party or the other to move the process forward. The mediator will take the time and make the effort to understand the position and interests of each party. The mediator will know when to start the process of making offers.

How Long Will the Mediation Last?

It is common to schedule mediations for either a half or one full day. More time should be scheduled for mediations that require extensive travel, multiple parties or involve complex factual or legal issues. It is best to build in a margin of "float" time for the mediation session.

Multiple day mediations have built-in challenges. The parties recess after the first day and go home to re-think their case in a light that supports their original position. Consequently, the parties begin the next day needing to "warm up" and get back into the solution/settlement mode.

Conclusion

There is no authoritative study on the success rate of mediation. However, the American Arbitration Association has reported that 85% of the mediations conducted under their administration have resulted in a settled resolution.

Mediation provides an opportunity for people to input how the process is designed and conducted. The parties are given an opportunity to confidentially express their interests and values without compromising their positions in front of the other parties. It provides the parties a sense of involvement and control over the dispute resolution process and the terms of a settlement. In fact, the mediation may be the last time where clients and their attorneys will remain in control of the resolution process.

Happy Mediating to All!

------------------------------------------------------------------------

News of the Firm

• Mountain States Super Lawyers named Robert F. Babcock as one of the top lawyers in the Intermountain States in the area of Construction Litigation Law. He was also named as one of the top seventy five lawyers in all categories for the Intermountain States and the only Utah construction lawyer to achieve that rating.

• Mountain States Super Lawyers named Kent B. Scott as one of the top lawyers in the Intermountain area in the area of Construction/Surety Law.

• Mountain States Super Lawyers named Justin E. Scott as one of the rising stars in the area of Construction Litigation.

• Jason Robinson taught two seminars in August, 2008 on the topic "Using a Mechanic's Lien to Get Your Money."

• Adam T. Mow has been invited to present The Top 5 Legal Issues of Building Information Modeling at the AIA 2009 National Convention and Design Exposition in San Francisco in the Spring of 2009.

• David Merrell, an associate of the firm is headed to the University of Washington where he will pursue an LL.M. degree in Asian and Comparative Law. With an LL.M. in Asian and Comparative Law, David hopes to build upon his experiences in the Middle East and Central Asia.

• Scott Degraffenried has recently joined the firm as an associate. Scott obtained his law degree from the University of Arizona State and is licensed to practice law in Arizona. He will be sitting to take the Utah State Bar in February, 2009.

    -----------------------------------------------------------------------

About BSB

About Babcock Scott & Babcock


FirmSite® by FindLaw, a Thomson Reuters business.

At Babcock Scott & Babcock, we represent clients throughout the Intermountain West and Utah, including Salt Lake City (SLC), Provo, Orem, West Valley City, Sandy, Draper, Murray, West Valley, Bountiful, Farmington, Kaysville, Layton, Logan, Price, St George, Midvale, Ogden, West Jordan, Taylorsville, South Jordan, Cottonwood Heights, Holladay, North Salt Lake, South Salt Lake, Park City, Riverton, Salt Lake County, Summit County, Utah County, Davis County, Cache County, Juab County, and Weber County. We also represent clients in Nevada, Idaho, Wyoming, California, Colorado, Arizona, Washington, Oregon, Montana, and New Mexico.

* The black and white photographs on this website are courtesy of the Utah State Historical Society.